By end of the WK25 2025, all pling works, deep pit retaining
wall and bracing works, geothermal piping works, road and underground outdoor
piping works for both temporary and permanent use, and more important over
60,000 m3 pit soil excavation and transportation works are completed earlier
than planned! These achievements are delivered in approx. 4 full-speed
construction months by BMPCE team for one of its EPC projects in Shanghai: the
Feature-Tec R&D, head-quarter, manufacturing and automation logistic
facility, in total with GFA over 60,000 m2.