VOLKSWAGEN Transmission in Tianjin - Winter Closure in record time

Release time:2014-12-10Hits:886 次

Returns a list of

After only 6 months of construction, Volkswagens' sizeable DL 382 Project in Tianjin was closed and heated from Dec. 10th, 2014. Applying the 'Think Blue' Sustainability Initiative of Volkswagen, a large number of energy-saving and -optimization features are realized, safeguarding the longterm efficiency of the facility. Parallel to the ongoing Fit-out and remaining M+E Works, the process installation started meanwhile, as scheduled from very beginning.